Proposed civil work under the SIP described below-

1. Re-excavation of Horai river = 7.00 Km

2. Re-excavation of Rupsa khal = 8.00 Km

3. Re-excavation of Rupsa branch-2 = 1.60 Km

4. Re-excavation of Rupsa branch-3 = 4.60 Km

5. Re-excavation of Rupsa branch-4 = 5.70 Km

6. Re-excavation of Rupsa branch-5 = 4.65 Km

7. Re-excavation of Nakkali khal = 0.75 Km

8. Re-excavation of Bhabanipur Khal= 0.35 Km

9. Re-excavation of Dhoparia khal = 0.75 Km

10.Re-excavation of Dattapara khal = 1.40 Km

11.Re-excavation of Arabaria khal = 0.40 Km

12.Re-excavation of Tarail Sibpur = 2.25 Km

13.Construction of Ck structure at Dattapara