Search tender



     
Total Awarded Tenders are: 63
SL Package No Tender NamePublish Date Closing Date Details Download
1 MAG-CWD-REG-I-W01-19 Manufacturing, Supplying & Installation of 14 Nos. M.S Lift Gate (size: 1.65m x 1.95m = 11 Nos. & 1.35m x 1.35m = 3 Nos.), 9 Nos. M.S. Flap gate (size: 1.65m x 1.95m = 7 Nos. & Size- 1.35m x 1.35m = 2 nos.) and 14 Nos. hand wheel type hoisting device for Bamunkhali-Barnali Sub-Project at Magura O&M Division, BWDB, Magura and 1 No. M.S. Lift gate (Size- 1.65m x 1.95m) with hand
(Contract Awarded)
29/10/2019 28/11/2019 Details Notice
Contract Awarded:
Contractor: M/S. Rashed Enterprise
Signing Date: 02/01/2020
Contract Value: 5074704.014
Commencement Date: 02/01/2020 Completion Date: 30/06/2020
2 MAG-CWD-REG-I-W01-18 Manufacturing, Supplying & Installation of 10 Nos. M.S Lift Gate (size: 1.65m x 1.95m = 7 Nos. & 1.35m x 2.35m = 3 Nos.) 8 Nos. M.S. Flap gate (size: 1.65m x 1.95m = 7 Nos., 1.35m x 1.35m = 1 No.), 10 Nos Hand Wheel Type Hoisting Device for BamunkhaliBarnali Sub-Project at Magura O&M Division, BWDB, Magura and 3 Nos Hand Wheel Type and 6 Nos Pedestal Type Hoisting Device for Ho
(Contract Awarded)
29/10/2019 28/11/2019 Details Notice
Contract Awarded:
Contractor: M/S. Rashed Enterprise
Signing Date: 02/01/2020
Contract Value: 4459725.027
Commencement Date: 02/01/2020 Completion Date: 30/06/2020
3 NAR-BB-KEX-I-W06-32 Re-Excavation of Bamonkhali khal from km. 0.000 to Km. 5.900 Km Jia khal from km 0.000 to Km 3.930 Km Shadhukhali khal from km. 0.000 to Km. 4.075 Km Shahabad khal From km. 0.000 to Km. 0.718 Km Solua khal From km. 0.000 to Km. 2.660 Km Total 17.283 Km in Bamunkhali-Barnali Sub-Project under South-West Area Integrated Water Resources Planning and Management Project year 2019-20
(Contract Awarded)
28/10/2019 27/11/2019 Details Notice
Contract Awarded:
Contractor: M/S Liton Treders
Signing Date: 13/01/2020
Contract Value: 21617355.22
Commencement Date: 14/01/2020 Completion Date: 13/01/2021
4 NAR-BB-WTC-I-W08-11 Construction of Typical Building of WMG Training centre Bamankhali-Barnali Sub-Project under South-West Area Integrated Water Resources Planning and Management Project (SWAIWRPMP) Phase- under Narail O&M Division BWDB Narail during the year 2019-2020.
(Contract Awarded)
28/10/2019 27/11/2019 Details Notice
Contract Awarded:
Contractor: M/S Jakaullah & Brothers
Signing Date: 05/02/2020
Contract Value: 3824445
Commencement Date: 06/02/2020 Completion Date: 05/02/2021
5 SD-CF-FB-I-W13-01 Construction of Foot Bridge at km. 1.212 on Baniabari khal near Dinabandhu Mandal house in Chatler-Fakurhat Sub-project, Upazila- Bhanga Dist.-Faridpur under Specialized Division, BWDB, Faridpur during the year 2019-20.
(Contract Awarded)
21/10/2019 21/11/2019 Details Notice
Contract Awarded:
Contractor: M/S Liton Treders
Signing Date: 11/02/2020
Contract Value: 9625355.204
Commencement Date: 12/02/2020 Completion Date: 30/06/2021
6 MAG-KA-REG-I-W01-16 Construction of Dorishaloi Surface Regulator (1 Vent-0.90mÃ?1.20m) over Flood Control Embankment at Km 0.600 in C/W Kalidaskhali-Arpara Sub-Project, under South-West Area Water Resources Planning and Management Project (SWAIWRPMP) Phase-2 Under Magura O&M Division BWDB during the Year 2019-20.
(Contract Awarded)
08/09/2019 07/10/2019 Details Notice
Contract Awarded:
Contractor: M/S. Mostafa & Sons
Signing Date: 26/11/2019
Contract Value: 13777269.431
Commencement Date: 26/11/2019 Completion Date: 20/06/2020
7 MAG-KA-REG-I-W01-15 Construction of Burikhali Surface Regulator (1 VENT- 0.90mX1.20m)AT KM 1.100 On Kalaidongle Khal in Kalidaskhali - Arpara Sub-Project within 'SAIWRPMP-AF"Upazila: Shalikha, District: Magura ,under Magura O&M Division, BWDB, Magura during the year 2019-20.
(Contract Awarded)
08/09/2019 07/10/2019 Details Notice
Contract Awarded:
Contractor: M/S Amin & Co.
Signing Date: 14/11/2019
Contract Value: 15026333.421
Commencement Date: 14/11/2019 Completion Date: 20/06/2020
8 MAG-BB-KEX-I-W06-29 Re-excavation of 8.477 km Bornali Khal from km 0.023 to km. 8.500 in C/W South-West Area Water Resources Planning and Management Project SWAIWRPMP Phase-2 under Bamonkhali-Bornali Sub Project Under Magura O&M Division BWDB during the Year-2019-20.
(Contract Awarded)
08/08/2019 09/09/2019 Details Notice
Contract Awarded:
Contractor: Noona Traders
Signing Date: 28/10/2019
Contract Value: 22025476.4
Commencement Date: 28/10/2019 Completion Date: 30/06/2020
9 RAJ-HR-WTC-I-W08-03 Construction of 4(Four) nos WMG Training Centre building at WMA-1, WMA-2, WMA-3 & WMA-4 under Horai River Sub-project during the year 2018-19.
(Contract Awarded)
03/07/2019 05/08/2019 Details Notice
Contract Awarded:
Contractor: SHAMS ENGINEERING & CONSTRUCTION LIMITED
Signing Date: 07/11/2019
Contract Value: 12616294.69
Commencement Date: 08/11/2019 Completion Date: 07/11/2020
10 SD-AB-WTC-I-W08-09 Construction of 03 nos WMG Training Centre for WMA-1, WMA-2 & WMA-3 in c/w AlfadangaBoalmari Sub-Project under SAIWRPMP-AF during the year 2019-2020.
(Contract Awarded)
07/07/2019 07/08/2019 Details Notice
Contract Awarded:
Contractor: M/S Azam Construction
Signing Date: 06/11/2019
Contract Value: 12332817.2
Commencement Date: 07/11/2019 Completion Date: 30/09/2020
11 SD-DK-WTC-I-W08-08 Construction of 03 nos WMG Training Centre for WMA-1, WMA-2 & WMA-3 in c/w DaduriaKandor Beel Sub-Project under SAIWRPMP-AF during the year 2019-2020.
(Contract Awarded)
07/07/2019 07/08/2019 Details Notice
Contract Awarded:
Contractor: M/S. Lipu Enterprise
Signing Date: 06/11/2019
Contract Value: 12333219.09
Commencement Date: 07/11/2019 Completion Date: 11/05/2020
12 SD-CF-WTC1-I-W08-07 Construction of 03 nos WMG Training Centre for WMA-1, WMA-2 & WMA-3 in c/w ChatlerFakurhat Sub-Project under SAIWRPMP-AF during the year 2019-2020.
(Contract Awarded)
07/07/2019 07/08/2019 Details Notice
Contract Awarded:
Contractor: Md. Rashidul Hasan
Signing Date: 06/11/2019
Contract Value: 12345826.92
Commencement Date: 07/11/2019 Completion Date: 30/09/2020
13 MAG-KA-WTC-I-W08-04 Construction of 02 Nos WMG Training Center Building of SIP-1 & SIP-2 in C/W Kalidaskhali- Arpara Sub-Project under South-West Area Water Resources Planning and Management Project (SWAIWRPMP) Phase-2 Under Magura O&M Division BWDB during the Year-2018-19 & 2019-20.
(Contract Awarded)
24/06/2019 24/07/2019 Details Notice
Contract Awarded:
Contractor: M/s. Md. Woahiduzzaman
Signing Date: 15/09/2019
Contract Value: 8505357.31
Commencement Date: 15/09/2019 Completion Date: 20/06/2020
14 MAG-BB-WTC-I-W08-06 Construction of 02 Nos WMG Training Center Building of SIP-1 & SIP-2 in C/W Bamonkhali-Bornali Sub-Project under South-West Area Water Resources Planning and Management Project (SWAIWRPMP) Phase-2 Under Magura O&M Division BWDB during the Year-2018-19 & 2019-20.
(Contract Awarded)
24/06/2019 24/07/2019 Details Corrigendum
Notice
Contract Awarded:
Contractor: M/s. Md. Woahiduzzaman
Signing Date: 15/09/2019
Contract Value: 8536427.11
Commencement Date: 15/09/2019 Completion Date: 30/06/2020
15 MAG-KA-WTC-I-W08-05 Construction of 02 Nos WMG Training Center Building of SIP-3 & SIP-4 in C/W Kalidaskhali- Arpara Sub-Project under South-West Area Water Resources Planning and Management Project (SWAIWRPMP) Phase-2 Under Magura O&M Division BWDB during the Year-2018-19 & 2019-20.
(Contract Awarded)
24/06/2019 24/07/2019 Details Notice
Contract Awarded:
Contractor: M/S. Shikder Enterprise
Signing Date: 15/09/2019
Contract Value: 8505357.137
Commencement Date: 15/09/2019 Completion Date: 30/06/2020
16 MAG-CWD-REG-I-W01-14 Supplying & fitting-fixing of 8 (Eight) Nos. M.S Lift Gate (Size: 1.670 m x 1.905 m) & 8 (Eight) Nos. Pedestal type hoisting device assy. for Katuli Regulator at Magura O&M Division, BWDB, Magura.
(Contract Awarded)
25/06/2019 29/07/2019 Details Notice
Contract Awarded:
Contractor: Sea-Shine International
Signing Date: 12/09/2019
Contract Value: 2131180.712
Commencement Date: 12/09/2019 Completion Date: 30/06/2020
17 MAG-KA-REG-I-W01-11 Repair of (1) Digolgram Regulator Over Digolgram Khal, (2) Kuatpur Regulator Over Kuatpur Khal & (3) Kathalbaria Regulator Over Kathalbaria Khal in C/W Kalidaskhali-Arpara Sub-Project, under South-West Area Water Resources Planning and Management Project (SWAIWRPMP) Phase-2 Under Magura O&M Division BWDB during the Year-2018-19 & 2019-20.
(Contract Awarded)
17/06/2019 18/07/2019 Details Notice
Contract Awarded:
Contractor: M/S Rupali Construction & SB(JV)
Signing Date: 15/09/2019
Contract Value: 10990598.731
Commencement Date: 17/09/2019 Completion Date: 02/09/2020
18 MAG-KA-REG-I-W01-10 Repair of (1) Chukinagor Regulator Over Kanuda Khal (2) Kuchiamora Regulator Over Kuchiamora Khal & (3) Kaitoly Check Structure Over Khalidaskhali Khal in C/W Kalidaskhali-Arpara Sub-Project, under South-West Area Water Resources Planning and Management Project (SWAIWRPMP) Phase-2 Under Magura O&M Division BWDB during the Year-2018-19 & 2019-20.
(Contract Awarded)
17/06/2019 18/07/2019 Details Notice
Contract Awarded:
Contractor: M/S Rupali Construction & SB(JV)
Signing Date: 15/09/2019
Contract Value: 12068397.694
Commencement Date: 17/09/2019 Completion Date: 02/09/2020
19 MAG-CWD-REG-I-W01-13 Supplying & fitting-fixing of 13 Nos. M.S Flap Gate & 13(Thirteen) Nos. chain pulley type hoist assy (Kuchiamore-3, Sukinagar- 3, Kathalbari- 2, Kalidaskhali- 3, Digalgram- 2) & 15 Nos. M.S Lift Gate (Kuchiamore-3, Kuatpur- 2, Chuki Nagar- 3, Kathalbaria- 2, Kalidaskhali- 3, Digalgram- 2), 15 Nos. padestal type hoisting device at Magura O&M Division.
(Contract Awarded)
21/05/2019 24/06/2019 Details Notice
Contract Awarded:
Contractor: M/S. Rashed Enterprise
Signing Date: 04/07/2019
Contract Value: 8107942.047
Commencement Date: 04/07/2019 Completion Date: 30/06/2020
20 MAG-CWD-REG-I-W01-12 Supplying & fitting-fixing of 2 (Two) Nos. M.S Lift Gate (Size: 1.910 m x 3.075 m) & 2 (Two) Nos. Padestal type hoisting device for Boyra Regulator at Magura O&M Division, BWDB, Magura : South-West Area Integrated Water Resources Planning & Management Project (Phase-2) under Central Workshop Division, BWDB, Tejgaon, Dhaka.
(Contract Awarded)
21/05/2019 24/06/2019 Details Notice
Contract Awarded:
Contractor: M/S. Moushumi Enterprise
Signing Date: 04/07/2019
Contract Value: 943848.283
Commencement Date: 04/07/2019 Completion Date: 30/06/2020
21 FAR-CWD1-REG-I-W01-08 Fabrication, Supplying & Installation of 5 Nos. M.S Lift Gate, 5 (Five) Nos. pedestal type hoisting device in connection with construction of Joyjhap Regulator (5-V) under Beel Sukunia Sub-Project of Faridpur O&M Division, BWDB, Faridpur : South- West Area Integrated Water Resources Planning & Management Project (Phase-2) under Central Workshop Division, BWDB, Tejgaon, Dhaka.
(Contract Awarded)
21/05/2019 24/06/2019 Details Notice
Contract Awarded:
Contractor: M/S. MYSHA TRADERS
Signing Date: 10/07/2019
Contract Value: 1467433.1
Commencement Date: 10/07/2019 Completion Date: 30/06/2020
22 RAJ-CWD-REG-I-W01-09 Fabrication, Supplying & Installation of 18 No. M.S Lift Gate (size: 1.65m x 1.95m = 4 No, 1.35m x 1.35m = 2 No, 1.65m x 2.54m = 12 No) M.S. Falp gate (size: 1.35m x 1.35m = 1 No & 4 No hand wheel, 6 padestal type hoisting device in connection with Repair of Regulator of Horai River Sub-Project at Rajbari O&M Division under Central Workshop Division.
(Contract Awarded)
06/03/2019 08/04/2019 Details Notice
Contract Awarded:
Contractor: Blue Star Enterprise
Signing Date: 16/05/2019
Contract Value: 4605324.964
Commencement Date: 16/05/2019 Completion Date: 28/06/2020
23 FAR-CWD-REG-I-W01-07 Fabrication, Supplying & Installation of 5 No. M.S Lift Gate (size: 1.65m x 1.95m, 5 No hand wheel type hoisting device in connection with repair of Regulator of Beel Sukunia Sub-Project at Faridpur O&M Division, BWDB, Faridpur: South-West Area Integrated Water Resources planning & Mangement Project (Phase-2) under Central Workshop Division, BWDB, Tejgaon, Dhaka.
(Contract Awarded)
06/03/2019 08/04/2019 Details Notice
Contract Awarded:
Contractor: M/S. Rashed Enterprise
Signing Date: 07/05/2019
Contract Value: 1200781.989
Commencement Date: 07/05/2019 Completion Date: 25/06/2020
24 SD-CWD-REG-I-W01-06 Fabrication, Supplying & Installation of 26 No. M.S Lift Gate (size: 1.65m x 1.95m = 14 No, 1.35m x 1.35m = 6 No, 1.65m x 2.54m = 6 No) M.S. Falp gate (size: 1.65m x 1.95m = 10 No & 21 No hand wheel, 6 padestal type hoisting device in connection with repair of Regulator of Alfadanga-Boalmari Sub-Project & Daduria-Kandor Beel Sub-Project at Faridpur Specialized Division.
(Contract Awarded)
06/03/2019 08/04/2019 Details Notice
Contract Awarded:
Contractor: M/S. Rashed Enterprise
Signing Date: 07/05/2019
Contract Value: 8120537.968
Commencement Date: 07/05/2019 Completion Date: 25/06/2020
25 MAG-KA-REG-I-W01-05 Construction of Boyra Regulator (2V-1.80M X 3.00M) at Km.0.300 of Kalidaskhali Khal in Kalidaskhali - Arpara Sub-Project within 'SAIWRPMP-AF"Upazila: Shalikha, District: Magura ,under Magura O&M Division, BWDB, Magura during the year 2018-19 & 2019-20.
(Contract Awarded)
05/02/2019 11/03/2019 Details Notice
Contract Awarded:
Contractor: M/S. Kamrul Enterprise
Signing Date: 23/04/2019
Contract Value: 28470156.501
Commencement Date: 23/04/2019 Completion Date: 21/06/2019
26 FAR-BS-REG-I-W01-04 Construction of Joyjhap Regulator 5V-1.50M x 1.80M at KM 0.495 of Kuchiamara Khal-01 in C/W Beel Sukunia Sub-Project under Southwest Area Integrated Water Resources Planning & Management Project 2nd Phase under Faridpur O & M Division during 2018-19 & 2019-20.
(Contract Awarded)
30/01/2019 04/03/2019 Details Notice
Contract Awarded:
Contractor: Azam Construction- M/S. Lipu Enterprise (JV)
Signing Date: 30/05/2019
Contract Value: 56183643.847
Commencement Date: 09/06/2019 Completion Date: 30/05/2020
27 SD-DK-REG-I-W01-03 Repair of Toiljuri 2-vent Hashemdia 1-vent and Kaliando 1- vent Regulator total 3 nos Regulator in c/w Daduria & Kandor Beel Sub-Project Upazila- Boalmari Dist.-Faridpur under Specialized Division BWDB Faridpur during the year 2018-19.
(Contract Awarded)
23/12/2018 22/01/2019 Details Notice
Contract Awarded:
Contractor: M/S.Azam Construction - M/S.Rafeea Construction (JV)
Signing Date: 28/03/2019
Contract Value: 9734180.023
Commencement Date: 31/03/2019 Completion Date: 11/02/2020
28 SD-AB-REG-I-W01-02 Repair of Hidadanga 6- vent Mohisherghop 4-vent Arpara 3-vent Utholi 3-vent and Helencha1-vent Regulator total 5 nos Regulator in c/w Alfadanga-Boalmari Sub-Project Upazila- Alfadanga Dist.-Faridpur under Specialized Division BWDB Faridpur during the year 2018-19.
(Contract Awarded)
23/12/2018 22/01/2019 Details Notice
Contract Awarded:
Contractor: M/S.Azam Construction - M/S.Rafeea Construction (JV)
Signing Date: 28/03/2019
Contract Value: 18278000
Commencement Date: 09/04/2019 Completion Date: 26/01/2020
29 MAG-KA-KEX-I-W06-28 Re-excavation of Kalidaskhali Khal from km Branch-1 Khal from km 0.000 to km. 1.250 = 1.250 km &Kalidaskhali Branch-2 Khal from km 0.000 to km. 1.790 = 1.790 km (Total = 8.140 Km) in C/W KalidasKhali-Arpar Sub Project under South-West Area Integrated Water Resources Planning and Management Project (SWAIWRPMP) Phase-2 under Under Magura O&M Division BWDB during the Year-2018-19.
(Contract Awarded)
19/12/2018 21/01/2019 Details Notice
Contract Awarded:
Contractor: M/S Jakaullah & Brothers
Signing Date: 20/02/2019
Contract Value: 17665792.167
Commencement Date: 20/02/2019 Completion Date: 20/06/2019
30 SD-AB-REG-I-W01-01 Construction of Tita Regulator (2v-1.50m×1.80m) at Km. 26.900 in Alfadanga-Boalmari Sub-Project, Upzila- Alfadanga, Dist.-Faridpur under Specialized Division, BWDB, Faridpur During The Year 2018-19.
(Contract Awarded)
18/12/2018 17/01/2019 Details Notice
Contract Awarded:
Contractor: M/S. Khandaker Shahin Ahmed & M/S Dawn Corporation (JV)
Signing Date: 05/03/2019
Contract Value: 35994668.14
Commencement Date: 06/03/2019 Completion Date: 30/06/2020
31 MAG-KA-KEX-I-W06-27 Re-excavation of 1. Digholgram Khal from km 0.000 to km. 6.150 = 6.150 km, 2. Digholgram Branch-1 Khal from km 0.000 to km. 0.900 = 0.900 km, 3. Digholgram Branch-2 Khal from km 0.000 to km. 0.550 = 0.550 km & 4. Digholgram Branch-3 Khal from km 0.000 to km. 1.300 = 1.300 km Total = 8.900 Km in C/W KalidasKhali-Arpar Sub Project under South-West Area Integrated Water Resources
(Contract Awarded)
02/12/2018 03/01/2019 Details Notice
Contract Awarded:
Contractor: M/S Jakaullah & Brothers
Signing Date: 03/02/2019
Contract Value: 9704797.775
Commencement Date: 04/02/2019 Completion Date: 21/06/2019
32 RAJ-HR-KEX-I-W06-25 Re-excavation of Rupsha Khal from KM 0.00 to 6.600 KM of Horai River Sub-Project in c/w " Southwest Area Integrated Water Resources Planning and Management Project - Additional Financial " in Upazilla Kalukhali & Baliakandi. Dist Rajbari under Rajbari O & M Division, BWDB, Rajbari during the year 2018-19 .
(Contract Awarded)
27/11/2018 27/12/2018 Details Notice
Contract Awarded:
Contractor: M/S Jakaullah & Brothers
Signing Date: 05/02/2019
Contract Value: 14606179.357
Commencement Date: 09/02/2019 Completion Date: 14/11/2019
33 SD-AB-KEX-I-W06-26 Re-excavation of 5.900 km Baniar Khal from km 0.000 to km 5.900 in c/w Alfadanga-Boalmari Sub-Project under SAIWRPMP-AF during the year 2018-2019.
(Contract Awarded)
19/11/2018 19/12/2018 Details Notice
Contract Awarded:
Contractor: Md.Shamimur Rahman
Signing Date: 28/01/2019
Contract Value: 15001166.376
Commencement Date: 28/01/2019 Completion Date: 27/01/2020
34 FAR-BS-KEX-I-W06-24 Re-excavation of Kuchiamara Khal-1 from km 0.000 to km 5.900 = 5900 m and Kuchiamara Khal-2 from km 0.000 to km 1.050 = 1050 m , Total = 6.950 km in c/w Beel Shukunia Sub Project under SAIWRPMP-2 under Faridpur O&M Division, BWDB, Faridpur, during the FY 2018-19.
(Contract Awarded)
31/10/2018 02/12/2018 Details Notice
Contract Awarded:
Contractor: Golam Md. Nasir
Signing Date: 29/01/2019
Contract Value: 13122476.816
Commencement Date: 30/01/2019 Completion Date: 30/05/2019
35 SD-CF-KEX-I-W06-22 Re-excavation of 4.641 km Jalukhali Khal, 0.720 km Langolkanda Khal total 5.361 km in c/w Chatler-Fakurhat Sub-Project under SAIWRPMP-AF during the year 2018-19.
(Contract Awarded)
17/09/2018 18/10/2018 Details Notice
Contract Awarded:
Contractor: M/S. Khandoker Shahin Ahmed
Signing Date: 18/11/2018
Contract Value: 10630394.625
Commencement Date: 18/11/2018 Completion Date: 17/11/2019
36 SD-AB-KEX-I-W06-23 Re-excavation of 6.010 km Hidadanga Khal, 2.600 km Burir Khal total 8.610 km in c/w Alfadanga-Boalmari Sub-Project under SAIWRPMP-AF during the year 2018-19.
(Contract Awarded)
17/09/2018 18/10/2018 Details Notice
Contract Awarded:
Contractor: M/S. Khandoker Shahin Ahmed
Signing Date: 18/11/2018
Contract Value: 10716965.92
Commencement Date: 18/11/2018 Completion Date: 17/11/2019
37 SD-CF-KEX-I-W06-21 Re-excavation of 1.770 km Sathroshi Khal, 1.290 km Baniabari Khal, 2.787 km Khatra Khal total 5.847 km in c/w Chatler-Fakurhat Sub-Project under SAIWRPMP-AF during the year 2018-19.
(Contract Awarded)
17/09/2018 18/10/2018 Details Notice
Contract Awarded:
Contractor: M/S. Khandoker Shahin Ahmed
Signing Date: 18/11/2018
Contract Value: 22387821.15
Commencement Date: 18/11/2018 Completion Date: 17/11/2019
38 RAJ-HR-KEX-I-W06-20 Re-excavation of 7.830 km of Horai River from km 25.000 to km 32.830 which is from Belgachi Regulator towards Rajapur Regulator of Horai River Sub-project in c/w Southwest Area Integrated Water Resources Planning and Management Project-2nd Phase in Upazilla- Rajbari Sadar Dist. Rajbari under Rajbari O&M Division, BWDB, Rajbari during the year of 2018-2019.
(Contract Awarded)
14/08/2018 13/09/2018 Details Notice
Contract Awarded:
Contractor: Noona Traders
Signing Date: 29/11/2018
Contract Value: 28665967.862
Commencement Date: 30/11/2018 Completion Date: 14/11/2019
39 RAJ-HR-KEX-I-W06-19 Re-excavation of 5.00 km of Horai River from km 20.000 to km 25.000 which is from Belgachi Regulator towards Rajapur Regulator of Horai River Sub-project in c/w Southwest Area Integrated Water Resources Planning and Management Project-2nd Phase in Upazilla- Rajbari Sadar Dist. Rajbari under Rajbari O&M Division, BWDB, Rajbari during the year of 2018-2019.
(Contract Awarded)
14/08/2018 13/09/2018 Details Notice
Contract Awarded:
Contractor: Mohammed Eunus & Brothers (Pvt.) Ltd.
Signing Date: 29/11/2018
Contract Value: 15938308.404
Commencement Date: 02/12/2018 Completion Date: 14/11/2019
40 RAJ-HR-KEX-I-W06-18 Re-excavation of 10.00 km of Horai River from km 10.000 to km 20.000 which is from Belgachi Regulator towards Rajapur Regulator of Horai River Sub-project in c/w Southwest Area Integrated Water Resources Planning and Management Project-2nd Phase in Upazilla- Rajbari Sadar Dist. Rajbari under Rajbari O&M Division, BWDB, Rajbari during the year of 2018-2019.
(Contract Awarded)
14/08/2018 13/09/2018 Details Notice
Contract Awarded:
Contractor: TAJWAR TRADE SYSTEM LIMITED
Signing Date: 29/11/2018
Contract Value: 18978151.127
Commencement Date: 30/11/2018 Completion Date: 14/11/2019
41 RAJ-HR-KEX-I-W06-17 Re-excavation of 5.00 km Horai River from km 5.000 to km 10.000 which is from Belgachi Regulator towards Rajapur Regulator of Horai River Sub-project in c/w Southwest Area Integrated Water Resources Planning and Management Project-2nd Phase in Upazilla-Rajbari Sadar Dist. Rajbari under Rajbari O&M Division, BWDB, Rajbari during the year of 2018-2019.
(Contract Awarded)
14/08/2018 13/09/2018 Details Notice
Contract Awarded:
Contractor: SA-SI & MD. RUHUL AMIN JV
Signing Date: 29/11/2018
Contract Value: 20898373.7
Commencement Date: 29/11/2018 Completion Date: 14/11/2019
42 RAJ-HR-KEX-I-W06-16 Re-excavation of 5.000 km of Horai River from km 0.000 to km 5.000 which is from Belgachi Regulator towards Rajapur Regulator of Horai River Sub-project in c/w Southwest Area Integrated Water Resources Planning and Management Project-2nd Phase in Upazilla- Rajbari Sadar Dist. Rajbari under Rajbari O&M Division, BWDB, Rajbari during the year of 2018-2019.
(Contract Awarded)
14/08/2018 13/09/2018 Details Notice
Contract Awarded:
Contractor: SA-SI & MD. RUHUL AMIN JV
Signing Date: 29/11/2018
Contract Value: 23015483.22
Commencement Date: 02/12/2018 Completion Date: 14/11/2019
43 RAJ-HR-KEX-I-W06-15 Re-excavation of 2.010 km of Horai River Intake from km 0.000 to km 2.010 , Padma River to Belgachi Regulator of Horai River Sub-project in c/w Southwest Area Integrated Water Resources Planning and Management Project-2nd Phase in Upazilla- Rajbari Sadar Dist. Rajbari under Rajbari O&M Division, BWDB, Rajbari during the year of 2018-2019.
(Contract Awarded)
14/08/2018 13/09/2018 Details Notice
Contract Awarded:
Contractor: Technip Corporation
Signing Date: 02/12/2018
Contract Value: 4828969.985
Commencement Date: 05/12/2018 Completion Date: 14/11/2019
44 RAJ-HR-KEX-I-W06-14 Re-excavation of 4.505 km Mora Kumar River from km 8.680 to km 13.185 of Rajbari portion Under Horai River Sub Project in c/w
(Contract Awarded)
08/08/2018 10/09/2018 Details Corrigendum
Notice
Contract Awarded:
Contractor: M/S Amin & Co.
Signing Date: 29/11/2018
Contract Value: 30445499.75
Commencement Date: 30/11/2018 Completion Date: 14/11/2019
45 RAJ-HR-KEX-I-W06-13 Re-excavation of 4.365 km Mora Kumar River from km 4.315 to km 8.680 of Rajbari portion Under Horai River Sub Project in c/w
(Contract Awarded)
08/08/2018 10/09/2018 Details Corrigendum
Notice
Contract Awarded:
Contractor: M/S Jakaullah & Brothers
Signing Date: 06/11/2018
Contract Value: 25871077.3
Commencement Date: 15/11/2018 Completion Date: 14/11/2019
46 RAJ-HR-KEX-I-W06-12 Re-excavation of Mora Kumar River from km.0.000 to km 4.315 = 4.315 km (Rajbari portion) Under Horai River Sub Project in c/w
(Contract Awarded)
08/08/2018 10/09/2018 Details Corrigendum
Notice
Contract Awarded:
Contractor: M/S Jakaullah & Brothers
Signing Date: 06/10/2018
Contract Value: 25303718.995
Commencement Date: 15/11/2018 Completion Date: 14/11/2019
47 SD-AB-ER-I-W04-02 Re-sectioning of 0.792km embankment from km. 23.700 to km. 24.492 & Construction of 1.450km retired embankment from km. 24.492/0.000 to km. 26.900/1.450 in c/w Alfadanga-Boalmari Sub-Project under SAIWRPMP-AF during the year 2017-2018 & 2018-2019.
(Contract Awarded)
25/07/2018 27/08/2018 Details Notice
Contract Awarded:
Contractor: M/S. Khandoker Shahin Ahmed
Signing Date: 11/09/2018
Contract Value: 37726976.438
Commencement Date: 11/09/2018 Completion Date: 10/09/2019
48 SD-CF-KEX-I-W06-08 Re-excavation of 8.430km Dosh Hajar Khal from km 0.000 to km 8.430 in c/w Chatler-Fakurhat Sub-Project under SAIWRPMP-AF during the year 2017-2018.
(Contract Awarded)
04/04/2018 07/05/2018 Details Notice
Contract Awarded:
Contractor: M/S Sarbick International
Signing Date: 10/06/2018
Contract Value: 15102829.757
Commencement Date: 09/06/2019 Completion Date: 09/06/2019
49 GOP-PC-RP-I-W03-01 River Bank Protection work at Daxmin Char Bhatpara to Village Joybangla along the Left Bank of Madhumati River from km. 0.878 to km 1.228 total 350 m under Southwest Area Integrated Water Resources Planning & Management Project-2nd Phase at Upazila-Kashiani District-Gopalganj under Gopalganj O & M Division BWDB Gopalganj during the year 2017-2018.
(Contract Awarded)
16/04/2018 21/05/2018 Details Corrigendum
Notice
Contract Awarded:
Contractor: Starlite Services Limited - M/S Udayan Builders (JV)
Signing Date: 20/06/2018
Contract Value: 65546312.243
Commencement Date: 20/06/2018 Completion Date: 30/12/2019
50 GOP-PC-RP-I-W03-03 River Bank Protection work at Daxmin Char Bhatpara to Village Joybangla along the Left Bank of Madhumati River from km. 1.578 to km 1.878 total 300 m under Southwest Area Integrated Water Resources Planning & Management Project-2nd Phase at Upazila-Kashiani District-Gopalganj under Gopalganj O & M Division BWDB Gopalganj during the year 2017-2018.
(Contract Awarded)
16/04/2018 17/05/2018 Details Notice
Contract Awarded:
Contractor: M/S Amin & Co.
Signing Date: 12/06/2018
Contract Value: 55554722.1
Commencement Date: 12/06/2018 Completion Date: 30/12/2019
51 GOP-PC-RP-I-W03-02 River Bank Protection work at Daxmin Char Bhatpara to Village Joybangla along the Left Bank of Madhumati River from km. 1.228 to km 1.578 total 350 m under Southwest Area Integrated Water Resources Planning & Management Project-2nd Phase at Upazila-Kashiani District-Gopalganj under Gopalganj O & M Division BWDB Gopalganj during the year 2017-2018.
(Contract Awarded)
16/04/2018 17/05/2018 Details Notice
Contract Awarded:
Contractor: M/S Amin & Co.
Signing Date: 12/06/2018
Contract Value: 61987775.72
Commencement Date: 12/06/2018 Completion Date: 30/12/2019
52 SD-CF-KEX1-I-W06-011 Re-excavation of 16.900 km Baliahati Khal from km. 0.000 to km. 16.900 in c/w Chatler-Fakurhat Sub-Project under SAIWRPMP-AF during the year 2017-18.
(Contract Awarded)
24/06/2018 26/07/2018 Details Notice
Contract Awarded:
Contractor: M/S. Khandoker Shahin Ahmed
Signing Date: 09/09/2018
Contract Value: 66613369.917
Commencement Date: 10/09/2018 Completion Date: 09/09/2019
53 MAG-KA-KEX-I-W06-09 Re-excavation of Kuatpur Khal from Km 0.000 to km. 3.900 = 3.900 km in C/W Kalidaskhali-Arpara Sub-Project under Southwest Area Integrated Water Resources Planning & Management Project (SAIWRPMP) Phase-2 under Magura O&M Division BWDB during the year 2017-18
(Contract Awarded)
18/04/2018 21/05/2018 Details Notice
Contract Awarded:
Contractor: M/S Amin & Co.
Signing Date: 25/06/2018
Contract Value: 7620295.919
Commencement Date: 25/06/2018 Completion Date: 24/06/2019
54 MAG-KA-KEX-I-W06-10 Re-excavation of Kanuda Khal from Km 0.000 to km. 12.700 = 12.700 km in C/W Kalidaskhali-Arpara Sub-Project under Southwest Area Integrated Water Resources Planning & Management Project (SAIWRPMP) Phase-2 under Magura O&M Division BWDB during the year 2017-18
(Contract Awarded)
18/04/2018 21/05/2018 Details Notice
Contract Awarded:
Contractor: M/S Jakaullah & Brothers
Signing Date: 25/06/2018
Contract Value: 24230015.4
Commencement Date: 25/06/2018 Completion Date: 24/06/2019
55 MAG-KA-ER-I-W04 -01 Re-sectioning of Flood Control Embankment from Ch. Km. 0.000 to km.12.600 12.600 Km. in KalidasKhali-Arpara sub Project under SWAIWRPMP-AF during the year 2017-2018 & 2018-2019.
(Contract Awarded)
07/03/2018 08/04/2018 Details Notice
Contract Awarded:
Contractor: M/S Liton Treders
Signing Date: 25/06/2018
Contract Value: 29836591.325
Commencement Date: 26/06/2018 Completion Date: 25/06/2019
56 I-W-08A Construction of Project Management Office (PMO) building at Faridpur [ADB loan No. 3302]
(Contract Awarded)
27/03/2017 27/04/2017 Details Notice
Contract Awarded:
Contractor: M/S Azam Construction
Signing Date: 29/06/2017
Contract Value: 39496620.65
Commencement Date: 29/06/2017 Completion Date: 28/12/2018
57 FAR-BS-KEX-I-W 06-07 Re-excavation of Beel Nalia Khal-1(Nikhordin to Kaijuri) from km 0.000 to 2.080=2.080 km & Beel Nalia Khal-2 (Mridhadangi) from km 0.000 to 6.500 km Total = (2.080+6.500) = 8.580 km in C/W Beel Shukunia Sub Project
(Contract Awarded)
28/02/2018 02/04/2018 Details Notice
Contract Awarded:
Contractor: MS NOOR CONSTRUCTION
Signing Date: 10/06/2018
Contract Value: 14561821
Commencement Date: 11/06/2018 Completion Date: 10/06/2019
58 MAG-KA-KEX-I-W06-06 Re-excavation of 4.350 km of Kuchiamora Khal from km 0.000 to km. 4.350 in C/W KalidasKhali-Arpara Sub-Project under SWAIWRPMP-AF during the year 2017-2018 & 2018-2019.
(Contract Awarded)
28/02/2018 02/04/2018 Details Notice
Contract Awarded:
Contractor: M/S Amin & Co.
Signing Date: 25/06/2018
Contract Value: 8255955.382
Commencement Date: 25/06/2018 Completion Date: 24/10/2019
59 MAG-KA-KEX-I-W06-05 Re-excavation of 2.750 km of Khathalbaria Khal from km 0.000 to km 2.750 & Re-excavation of 1.140 km of Khathalbaria Branch Khal from km 0.000 to km. 1.140 in C/W KalidasKhali-Arpara Sub-Project under SWAIWRPMP-AF during the year 2017-2018 & 2018-2019
(Contract Awarded)
28/02/2018 02/04/2018 Details Notice
Contract Awarded:
Contractor: M/S Amin & Co.
Signing Date: 25/06/2018
Contract Value: 4580684.514
Commencement Date: 25/06/2018 Completion Date: 24/09/2019
60 SD-CF-KEX-I-W06-04 Re-excavation of 1.620km Hamiddi Khal 2.150km Rajkanda Khal 1.040km Charakhali Khal 0.720km Ajgor Munshir Khal total 5.530km in c/w Chatler-Fakurhat Sub-Project under SAIWRPMP-AF during the year 2017-2018.
(Contract Awarded)
25/02/2018 28/03/2018 Details Notice
Contract Awarded:
Contractor: Rahid Enterprise JV
Signing Date: 07/06/2018
Contract Value: 14756518.232
Commencement Date: 07/06/2018 Completion Date: 06/06/2019
61 SD-CF-KEX-I-W06-03 Re-excavation of 4.375km Hashemdia Khal from km 0.000 to km 4.375 in c/w Chatler-Fakurhat Sub-Project under SAIWRPMP-AF during the year 2017-2018.
(Contract Awarded)
25/02/2018 28/03/2018 Details Notice
Contract Awarded:
Contractor: M/S Sarbick International
Signing Date: 10/06/2018
Contract Value: 11487025.621
Commencement Date: 10/06/2018 Completion Date: 09/06/2019
62 SD-CF-KEX-I-W06-02 Re-excavation of 7.500km Fukurhat Khal from km 7.000 to km 14.500 in c/w Chatler-Fakurhat Sub-Project under SAIWRPMP-AF during the year 2017-2018.
(Contract Awarded)
25/02/2018 28/03/2018 Details Notice
Contract Awarded:
Contractor: M/S Amin & Co.
Signing Date: 11/06/2018
Contract Value: 26208026.105
Commencement Date: 11/06/2018 Completion Date: 10/06/2019
63 SD-CF-KEX-I-W06-01 Re-excavation of 7.000km Fukurhat Khal from km 0.000 to km 7.000 in c/w Chatler-Fakurhat Sub-Project under SAIWRPMP-AF during the year 2017-2018.
(Contract Awarded)
18/02/2018 20/03/2018 Details Notice
Contract Awarded:
Contractor: M/S Liton Treders
Signing Date: 22/05/2018
Contract Value: 34,047,249.78
Commencement Date: 22/09/2018 Completion Date: 21/05/2019